BSEE informed that recently, several fires occurring during hot work have been reported. Hot work is any job with the potential to create an ignition source, such as an open flame, sparks, or high temperatures. Examples of hot work include welding, using acetylene torches, and grinding and cutting metal.

#1 Incident 1: As a construction crew removed skid pads with a torch on the top deck, slag and sparks fell through the grating onto the manway cover of the water skimmer below, igniting a fire. The fire self-extinguished shortly thereafter as the fire watch was securing a dry chemical fire. The water skimmer had been cleaned a week prior in preparation for vessel entry but had not been deemed inert, and the oil dump lines were later found to be full of flammable condensate. Although gas was not detected in the area around the skimmer before starting work, an 8% lower explosive limit was detected at the manway cover later. Workers used fire retardant tarps earlier in the job, but when the workers moved to a new location above the water skimmer, they did not take the retardant tarps with them.

#2 Incident 2: While cutting grating with an acetylene torch, falling sparks ignited gas leaking from a pinhole on a gas sales riser located 15 feet below the grating. The fire watch noticed and stopped the job. A worker used a 30-pound ABC fire extinguisher to extinguish the flame. Although a gas detector had measured a 0.0% lower explosive limit before the work started, the gas leak occurred in an area not easily accessible for inspection or gas monitoring.

#3 Incident 3: Before a construction crew removed steel bar grating from beneath a building, it was elevated several inches to provide a distance barrier between the subfloor and the torch cutting below. Saltwater was used to saturate the subfloor, and water was re-applied periodically. The crew finished their work, and the fire watch remained on location for an additional 30 minutes. A fire was noticed on the lower side of the building 15 minutes later, which was extinguished with the saltwater hose. It was found that the distance barrier may not have been sufficient to prevent a fire, and that the combustible surfaces should be saturated with water during the fire watch period as well as during the job.

BSEE recommends that operators and contractors consider: